Skip to content
An official website of the Velocity Interoperability Network

Port Charges

The Ports Authority of the Velocity Interoperability Network sets and collects the charges payable for the use of its ports and terminals: port dues on every vessel that enters port limits, pilotage and towage on every movement for which they are provided, handling charges on the cargo worked across the quay, storage charges on cargo that remains beyond its free period, and the other charges set out below. The schedule on this page is the whole of the Authority's tariff. No other charge is made for the use of the ports.

All sums are expressed in credits. The schedule takes effect on Monday 7 September 2026 and remains in force to 31 December 2026, and replaces the interim charges under which the ports operated during the transition period. The schedule for 2027 will be published in November 2026 and announced in the Newsroom.

Schedule in force from 7 September to 31 December 2026

Charges are invoiced to the vessel's registered agent within three working days of departure and are payable within 30 days. The Authority does not accept payment at its terminals or gates. Enquiries about an invoice should quote the vessel and the invoice number.
400
Credits, the minimum port dues charged on a vessel call
120
Credits, the flat charge on coastal and inland craft under 500 gross tonnes
3
Working days after departure within which charges are invoiced
30
Days from the date of invoice within which charges are payable

Port dues. Port dues are charged on each call at the rate per gross tonne shown below, subject to the minimum charge for the category. Gross tonnage is that recorded on the vessel's tonnage certificate. A vessel calling at more than one port of the Network on the same voyage pays dues once, at the rate for the first port entered. A vessel entering port limits and leaving without berthing pays half the dues that would otherwise be charged.

Port dues by vessel category, from 7 September 2026
Vessel categoryRate per gross tonneMinimum chargeBasis
Container vessel0.42400Per gross tonne, each call
Dry bulk carrier0.36400Per gross tonne, each call
Tanker and liquid bulk carrier0.48600Per gross tonne, each call
General cargo and project cargo vessel0.38400Per gross tonne, each call
Roll-on roll-off vessel0.34400Per gross tonne, each call
Passenger and ferry vessel on a scheduled service0.22250Per gross tonne, each call
Coastal or inland craft under 500 gross tonnesNot applicable120Flat charge, each call
Vessel entering for shelter or repair only0.18200Per gross tonne, each call

Pilotage. Pilotage is charged on each movement into, within or out of port limits at the rate for the vessel's length overall. The lengths at which pilotage is compulsory, and the ports at which it applies, are set out on the Vessel Arrivals and Berthing page. Where a pilot is detained on board beyond four hours by a delay for which the vessel is responsible, a further 210 credits is charged for each hour or part of an hour.

Pilotage charges by vessel length, each movement
Vessel length overallCharge in creditsNotes
Under 60 metres180Charged only where a pilot is requested
60 to 99 metres260Compulsory at Northgate Harbour and Meridian Basin
100 to 149 metres420Compulsory at all ports
150 to 219 metres640Compulsory at all ports
220 metres and over980Compulsory at all ports; includes the second pilot
Shift between berths, any lengthHalf the rate aboveNot charged where the shift is at the Authority's convenience
Pilot ordered and not usedHalf the rate aboveWhere the order is cancelled less than four hours before boarding

Towage. Towage is charged for each tug on each movement. The number of tugs required by a vessel's length is set out on the Vessel Arrivals and Berthing page; a vessel that orders more tugs than are required pays for those it orders. No charge is made where the harbour master orders tugs to a vessel in the interest of the safety of the port.

Towage charges, each tug
ServiceCharge in creditsBasis
Tug, first hour or part of an hour760Each tug, each movement
Tug, each further half hour290Each tug, each movement
Tug standing by without making fast380Each tug, each hour or part of an hour
Tug ordered and cancelled within two hours of the movement380Each tug
Tug attending a vessel with a defect affecting its manoeuvring1,140Each tug, first hour
Emergency call-out of a tug by the harbour masterNo chargeWhere the Authority orders the movement in the interest of the port

Cargo handling. Handling charges are made for the work of the Authority's cranes, plant and staff in discharging cargo from a vessel to the quay and in loading cargo from the quay to a vessel, including the tally. They do not include carriage beyond the terminal gate, which is arranged by the cargo owner. Where a vessel works its own gear at Westbrook Wharf the charge per tonne is reduced by 30 per cent.

Cargo handling charges, from 7 September 2026
CargoBasisCharge in creditsNotes
Container, 20 ft, ladenPer move128Discharge or load, quay to vessel
Container, 40 ft or longer, ladenPer move192Discharge or load, quay to vessel
Container, empty, any lengthPer move74Discharge or load, quay to vessel
Container carrying dangerous goodsPer moveRate above plus 60 per centIncludes segregated stowage on the quay
Out-of-gauge or over-height containerPer moveRate above plus 85 per centBy prior arrangement only
Dry bulk cargoPer tonne3.10Grab discharge to silo or road vehicle
Liquid bulk cargoPer tonne2.40Through the jetty pipelines to nominated shore tanks
Break-bulk and general cargoPer tonne9.60Quay to vessel or vessel to quay
Project cargo and heavy lifts over 60 tonnesPer lift1,850Requires an approved lifting plan
Roll-on roll-off unit, accompaniedPer unit44Driven on or off by the carrier
Roll-on roll-off unit, unaccompaniedPer unit96Includes movement by the Authority's tractor
Ferry passenger on a scheduled servicePer passenger3.20Charged to the operator, not the passenger

Storage. Cargo may remain at a terminal without charge for the free period shown. Storage is then charged for each day or part of a day until the cargo is removed, counted from the end of the free period. Cargo remaining after 30 days may be removed to the Authority's store at the owner's expense and, after 90 days, disposed of under the Authority's rules; the storage charge continues to run in the meantime. The handling rules that govern free periods and removal are set out on the Cargo and Handling page.

Free storage periods and storage charges
CargoFree periodCharge after the free period, in credits
Import container5 days from discharge38 per container, per day
Export container7 days before the loading window38 per container, per day
Refrigerated container, connected3 days from discharge96 per container, per day
Break-bulk and general cargo5 days from discharge4.20 per tonne, per day
Project cargo and heavy lifts3 days from discharge18.00 per tonne, per day
Roll-on roll-off unit3 days from discharge52 per unit, per day
Dry bulk in the Northgate silos7 days from discharge1.90 per tonne, per day
Empty container on the quay48 hours46 per container, per day

Other charges. The charges below are made for services provided on request and for the surcharges that arise where the handling rules are not observed. A surcharge is made in addition to, and not instead of, the ordinary handling charge.

Other charges and surcharges
Service or surchargeCharge in creditsNotes
Weighbridge, verified gross mass68 per containerAt Southbank and Meridian Basin
Extended working outside published hours1,240 per gang, per shiftBy arrangement with the terminal office
Work on a public holiday of the Network1,860 per gang, per shiftBy arrangement with the terminal office
Refrigerated container point42 per container, per dayIncludes four-hourly temperature checks
Undeclared cargo found on board640 per consignmentIn addition to the handling charge
Container presented without a verified gross mass220 per containerThe container is held until a mass is supplied
Waste, oily residue and sewage reception310 per collectionAt Southbank and Northgate only
Fresh water supplied alongside6.40 per tonneMinimum charge 120 credits
Quay space for repair or lay-up1,450 per berth, per dayBy written agreement only
Copy of a tally sheet or cargo recordNo chargeOne copy to the agent or cargo owner

Invoicing and payment. The Authority invoices the vessel's registered agent, who is responsible to the Authority for the charges on the call whether or not it has recovered them from the vessel's owner or the cargo owner. The steps below apply to every call.

  1. Step 1: Charges are recorded as they arise

    Port dues are recorded on the vessel's arrival, pilotage and towage on each movement, handling on each move or tonne worked, and storage at the end of each free period. The records are drawn from the harbour master's log and the terminal tally.

  2. Step 2: A statement is sent on departure

    The agent receives a statement of the charges recorded against the call on the day the vessel sails. The statement is the agent's opportunity to identify a movement, a move or a tonnage that is wrongly recorded.

  3. Step 3: The invoice is issued within three working days

    The Authority invoices the registered agent within three working days of the vessel's departure. Storage charges that continue after departure are invoiced separately at the end of each week in which they accrue.

  4. Step 4: Payment falls due within 30 days

    Charges are payable within 30 days of the date of the invoice. Interest accrues on a sum outstanding after that date at one per cent for each month or part of a month.

  5. Step 5: Cargo is released against payment

    Import cargo is released at the gate once it has been cleared by the Customs Service and any storage charges have been paid. The Authority may decline to accept a further vessel from an agent whose account has been outstanding for more than 60 days.

  6. Step 6: A charge may be questioned within 30 days

    An agent or cargo owner who considers a charge to be wrongly made writes to the Authority within 30 days of the invoice, stating the vessel, the invoice number and the item questioned. The Authority answers in writing within ten working days, and the sum in question is not treated as overdue while the question is open.

Remission and exemption. The Authority may remit a charge in whole or in part where a vessel enters for shelter, to land a person who is ill or injured, or to assist another vessel; where a movement is made at the Authority's own convenience; or where a delay is caused by a failure of the Authority's equipment. Vessels of the Network engaged on official service are exempt from port dues, pilotage and towage, but pay handling and storage charges in the ordinary way.

Questions about the schedule, about an invoice, or about the remission of a charge may be sent to contact@ports.gov.vin. For the terminals to which these charges relate, see Terminals; for the volumes on which they are levied, see Statistics; and for answers to common questions, see the frequently asked questions.